Improving the management of civil litigation, to improve access to justice
Submitting Institution
University of OxfordUnit of Assessment
LawSummary Impact Type
LegalResearch Subject Area(s)
Law and Legal Studies: Law
Summary of the impact
An extensive body of research by Adrian Zuckerman has resulted in a
significant improvement in
the management of civil trials in England and Wales, and therefore to an
improvement in access to
justice for litigants. Zuckerman made a sustained argument that litigants
are entitled only to a fair
share of court resources, and not to an excessive share. His
critical defence of this view changed
the courts' use of their powers under the Civil Procedure Rules 1998
(CPR), and persuaded the
Civil Procedure Rules Committee to change the rules themselves, regarding
sanctions for failure to
comply with procedural rules and court orders. The result is an important
move toward the
approach that Zuckerman has advocated: that parties should not be allowed
to depart from
deadlines imposed by rules and court orders unless they could not
reasonably have complied in
time, or had good reasons for the default.
Underpinning research
The authoritative work on civil procedure, Zuckerman on Civil
Procedure: Principles of Practice
[R1] (`Civil Procedure'), provides a coherent and detailed
account of litigation under the CPR
system. It explains the purpose of the CPR, how the courts interpret and
apply the CPR, the
principles that govern the exercise of judicial discretion, and how judges
ought to exercise their
extensive case management powers.
Adrian Zuckerman, Professor of Civil Procedure at Oxford since 1973,
argued that the CPR
introduced a three-dimensional concept of civil justice, which required
the court to deliver
judgments that are not only correct but are also reached by a
process that is efficient and
expeditious. He showed that this new concept had far-reaching
implications in practice, because
the new commitment to efficiency calls for consistent enforcement of
deadlines and other process
requirements. In order to prevent litigants from protracting litigation
unnecessarily, Zuckerman
argued, the court should refuse to allow parties to depart from deadlines
imposed by rules and
court orders unless they could not reasonably have complied in time, or
had good reasons for the
default. It is all too tempting for judges, in their role in giving effect
to the CPR, to conclude or to
assume that they should do whatever it takes — and should inflict whatever
delay or cost may result
to the parties — in order to reach the true substantive determination of a
claim. Civil Procedure
explains the reasons against this approach: they lie both in the fact that
a litigant has no right to a
disproportionate share of the community's resources in the administration
of civil justice, and also
in the right of a party in civil litigation to be protected from abuse by
an adverse party in the
litigation process. Civil Procedure also argued in particular
(para 4.145) that an application for
extension of time made after the expiry of the limitation period should be
treated with greater
caution because "the claimant is effectively asking the court to disturb a
defendant who is by now
entitled to assume that his rights can no longer be disputed."
Having set out these principles in Civil Procedure, Zuckerman
addressed their particular
implementation in a series of articles in Civil Justice Quarterly
[R2-5], criticising the judicial
tendency to tolerate non-compliance with court orders. As one of the
principal reasons for this
unfortunate tendency Zuckerman identified the wording of CPR 3.9, which
set out the
considerations that the court must take into account when dealing with an
application to obtain
relief from sanctions imposed as a result of failure to comply with a
rule, practice direction or court
order.
References to the research
[R1] Zuckerman AAS, Zuckerman on Civil Procedure: Principles
of Practice (2nd edn, Sweet &
Maxwell 2006 [f.p. 2003]) (esp. chap 4, 10).
[R2] Zuckerman, "Enforcing compliance with deadlines", (2004) 23
Civil Justice Quarterly 231.
[R3] Zuckerman, "Service of the Claim Form", (2005) 24 Civil
Justice Quarterly 401.
[R4] Zuckerman, "Service of the Claim Form", (2006) 25 Civil
Justice Quarterly 127.
[R5] Zuckerman, "New provisions for service — A great improvement
threatened by discretion."
(2009) 27 Civil Justice Quarterly 1.
Details of the impact
Zuckerman's research in civil procedure has had impact in three distinct
ways:
(1) Zuckerman's argument was taken up and applied by the court in
relation to service of the claim
form in both City & General (Holborn) Ltd v Structure Tone Ltd
[2009] [C3] and Imperial Cancer
Research Fund v Ove Arup & Partners Ltd [2009] [C4]. In
these cases, the Court of Appeal
accepted the principle, advocated by Zuckerman, that even where an
application for extension of
time for service of the claim form has been made before the expiry of the
deadline, permission
should be granted only where there was good reason for not serving in
time. These cases built on
an earlier line of decisions relying on Zuckerman's research: (Hashtroodi
v Hancock [2004] EWCA
Civil 652, [17]; Maggs v Marshall [2005] EWHC 200 (QB); Collier
v Williams [2006] EWCA Civ 20,
[2007] 1 All ER 991, [85].
(2) Zuckerman's approach to applications for extension of time made after
the expiry of the
limitation period [R2] was adopted by the Court of Appeal in Cecil
v Bayat [2011] [C5]. The court
relies very extensively on Zuckerman's research at [77]-[78], and
at [94]. The matter is
determined to be not only one of formalities or expectations, but of
fundamental reasonableness:
`The matter goes further than that, because, whatever the expectations of
a defendant who
bears any relevant limitation period in mind, the fact is that an
extension of time for service
does effectively extend the period (primarily a matter of limitation)
during which a claimant
can do nothing to bring his litigation formally to the notice of his
defendant. That larger point
was the subject matter of another observation of Professor Zuckerman (at
para 4.134): "The
need for placing a time limit on service of the claim form is dictated by
the need for finality in
litigation and by the very existence of limitation periods. The period
allowed for service seeks
to ensure that the uncertainty of litigation is not unreasonably extended.
(...)" [C5, at 78]
(3) The Civil Procedure Rules Committee revised the CPR in accordance
with Zuckerman's
argument in [R1]. The proposal that the court should give higher
priority to the need to enforce
rules and court orders was accepted in the Jackson Review of Civil
Litigation Costs, Final Report,
2010 [C1], and has been implemented in the revised CPR 3.9 with
effect from 1 April 2013 [C2].
Lord Justice Jackson's Review commented as follows on Zuckerman's
criticism of the
flawed enforcement of case management timetables [C1, pp.386-387]:
"2.1 ... Professor Adrian Zuckerman presented a paper on litigation
management.
Professor Zuckerman argued that the courts must deliver judgments within a
reasonable
time and at reasonable cost. The courts, like the National Health Service,
are a public
service. Their function is to adjudicate disputes with available
resources. Court users are
only entitled to their fair share of court resources. At the moment
judges, following the
precept of CPR 3.8, 3.9 and 3.10 are far too indulgent to litigants in
default. This causes not
only delay but also unproductive waste of court resources in dealing with
the effects of
litigant failure to meet deadlines. It is only in truly extreme
circumstances that the courts will
strike out a party which is in default. Such extreme circumstances are
exemplified by
Marine Rescue Technologies Ltd v Burchill [2007] EWHC 1976 (Ch). After
reviewing the
tortuous history of that case Professor Zuckerman stated:
"By no stretch of the imagination can this be considered an efficient use
of court resources,
nor was it fair to other litigants waiting in the queue, nor did it
provide effective protection to
the defendant from being unnecessarily subjected to 6 years of futile
litigation... The main
responsibility for this state of affairs must be accepted by the Court of
Appeal. The Court of
Appeal has steadfastly declined to develop a coherent policy for enforcing
compliance with
rules and case management directions. Its refusal to provide leadership in
this regard is
nowhere more apparent than in relation to its interpretation of CPR 3.9."
2.2 A little later Professor Zuckerman stated:
"Even more corrosive of good management practice is the Court of Appeal's
inability to
speak with one voice. The understanding of the overriding objective varies
greatly amongst
its judges, with some judges still holding the view that their only duty
is to decide cases
according to the facts and the law, no matter how long it takes and how
much it costs.
Management standards will not improve unless the Court of Appeal is
willing to provide
leadership. To do so it would have to revise its approach to the
enforcement of compliance
with case management directions and therefore to the operation of CPR 3.9.
It would have
to adopt a policy that gives practical expression to the need to ensure
that court resources
are properly utilised. This means, amongst others, that a litigant who has
failed to take
advantage of the opportunity of prosecuting his case will not get another
opportunity, unless
he has been prevented from doing so by circumstances beyond his control."
2.3 Professor Zuckerman in his oral address (though he did not touch on
this in his paper)
commended the approach which is canvassed as one possible way forward in
PR
paragraph 43.4.21. He concluded by arguing that the civil justice system
like all other public
services must be adequately managed, so as to deliver a satisfactory
service. He added:
"The management task that the court is expected to discharge is relatively
uncomplicated:
to ensure that case management directions are implemented as laid down,
unless a
change of circumstances demands otherwise. But this simple task requires
the court to
abandon its almost religious attachment to the one dimensional
understanding of justice
and accept that doing justice means more than delivering a judgment on the
merits; that
time and the use of resources are just as significant imperatives of
justice."
2.4 Unsurprisingly Professor Zuckerman's presentation provoked a measure
of
disagreement and lively discussion. One speaker made the point that if the
court sets an
unrealistic timetable, as sometimes happens, that encourages a culture of
noncompliance.
In a vote at the end of this discussion 32 people agreed with Professor
Zuckerman's thesis,
14 disagreed and there were 22 abstentions." [C1]
Zuckerman's argument, summarized above by Lord Justice Jackson,
ultimately persuaded the
Rules Committee that "courts at all levels have become too tolerant of
delays and non-compliance
with orders. In so doing, they have lost sight of the damage which the
culture of delay and non-
compliance is inflicting upon the civil justice system. The balance
therefore needs to be redressed."
[C1, p.397]. Relying expressly and directly on Zuckerman's work,
the Review therefore
recommended:
"86 The courts should be less tolerant than hitherto of unjustified
delays and breaches of
orders. This change of emphasis should be signalled by amendment of CPR
rule 3.9." [C1,
p.469].
This recommendation was soon taken up in practice. The 2010 Report,
accepting and relying on
the evidence in Zuckerman's research, persuaded the Rules Committee to
revise CPR 3.9 with
effect from 1 April 2013. The revised CPR [C2] now states:
"(1) On an application for relief from any sanction imposed for a failure
to comply with any
rule, practice direction or court order, the court will consider all the
circumstances of the
case, so as to enable it to deal justly with the application, including
the need-
(a) for litigation to be conducted efficiently and at proportionate cost;
and
(b) to enforce compliance with rules, practice directions and orders."
This amendment gave legal authority to the argument of Zuckerman's
research, and restored the
binding force of case management rules and court orders. The result was to
reduce a litigant's
opportunity to inflict delay and cost on another party and on the system.
The impact of the research
means significantly improved access to judgment for civil litigants
throughout England and Wales.
Sources to corroborate the impact
[C1] Lord Justice Jackson, Review of Civil Litigation Costs:
Final Report (2010)
[C2] Amendment of CPR 3.9 -Rupert Jackson's note to the Rule
Committee re Rule 3.9 (second
draft) [June 2011]
[C3] City & General (Holborn) Ltd v Structure Tone Ltd,
18 August 2009, Queen's Bench Division
(Technology & Construction Court) EWHC 2139 (TCC), [27]
[C4] Imperial Cancer Research Fund v Ove Arup & Partners
Ltd, 23 June 2009, Queen's Bench
Division (Technology & Construction Court) EWHC 1453 (TCC), [9]
[C5] Cecil v Bayat Court of Appeal (Civil Division),
[2011] EWCA Civ 135, 18 February 2011
EWCA Civ 135, [77]-[78], [94]