Improving Megaproject Performance through Better Decision Making
Submitting Institution
University of OxfordUnit of Assessment
Business and Management StudiesSummary Impact Type
PoliticalResearch Subject Area(s)
Information and Computing Sciences: Information Systems
Summary of the impact
80% of all government policies are delivered through large-scale projects and programmes. In the
private and the public sector alike they are key to innovation, change, and growth. However, they
often go wrong. The research has impacted on the performance of a number of projects by
changing the way projects are planned, managed, and assured. The impact is the result of the
research programme of the BT Centre for Major Programme Management (BTC), a research
centre of the Saïd Business School. The research has had an impact on a wide range of
management and policy issues in the UK and internationally. This case study highlights three
examples. The first is impact on the UK government's assessment of projects through work with
the National Audit Office (NAO). The second is innovation of professional services at McKinsey &
Company. The third is impact on the largest infrastructure investment in the developed world - the
California High Speed Rail project.
Underpinning research
Research team at Oxford includes:
- Prof. Bent Flyvbjerg, BT Professor and Chair of Major Programme Management — Principal
Investigator, at Oxford since 04/2009
- Dr. Chantal Cantarelli, Research Fellow, managed the research stream on transport
infrastructure, at Oxford since 04/2011
- Alexander Budzier, Doctoral student (2009- to present) — managed the research stream on
ICT, at Oxford since 09/2009
- Dr. Atif Ansar, Research Fellow, research assistance on transport infrastructure stream, at
Oxford since 09/2006
- Dr. Allison Stewart, Doctoral student (2009-2012), research assistance on ICT and
transport infrastructure stream, at Oxford 09/2008-12/2012.
The research team's work aimed to better understand and subsequently innovate in the way
megaprojects and major programs are delivered. Megaprojects are transformative, complex, and
time-bound undertakings, with an investment of at least USD 1 billion. They can be found in all
industries and focus on delivering organisational change, introducing technologies, or building
physical assets. Innovations in the last 70 years have, however, not contributed to a significant
improvement in performance as cost overruns, schedule delays, and benefit shortfalls are still
widespread. Therefore the research program aimed to further understanding of the importance and
impact of the under-researched front-end management of these megaprojects.
The research program was designed in multiple streams to use the same methodology to
systematically build large comparable datasets of project performance across transport
infrastructure, and information and communication technology (ICT). The unique size of the
datasets has enabled empirical comparisons that previously were not possible. Furthermore, the
data were used to test theories on biases in decision-making, principal-agent relationships, and
complexity management. Findings have been fed back into policy and practice via multiple
publications, conference presentations, teaching, consultancy, and media outreach.
The findings from the first research stream, transport infrastructure, explored the determinants of
budget overruns, schedule delays, and benefit shortfalls. The research project built a database of
1,493 infrastructure projects from 34 different countries, dating back 90 years. The research
focussed on structural and temporal determinants of optimism bias and strategic
misrepresentation, which are both root causes of cost overruns, schedule delays, and benefits
shortfalls in megaprojects. Prior research argued that a key to addressing the root causes of these
is to shift from an inside view of projects to the outside view, i.e. to replace subjective judgements
with objective empirical data. This research developed an eight-step theoretical process model to
conduct quality control and due diligence of decision making on megaprojects. The process was
tested on a real-life example, which has been documented in a case study. This research has been
published in high ranking articles, among others [Section 3: R1, R2, R3, R4].
The second, more recent, stream of the research, ICT, challenged prevailing assumptions about
social and technical complexity as a factor influencing project performance. The research stream
collected a global sample of nearly 4,300 projects from 189 public and private sector organisations.
The key finding showed that in the performance of ICT projects, outliers matter more than for the
typical project. The data showed that the rate of outliers is higher in ICT projects than in any other
field of project management. Furthermore the research found that the social complexity of projects
dominates the technical complexity. Moreover it showed that a particular indicator of risk is the
project's length but not its size. Lastly, the research stream identified early indicators that might
help with catching high-risk projects. Preliminary results of this research have only been published
very recently as a working paper, conference paper, and in the Harvard Business Review, which
featured the work as the No. 1 Idea to Watch [R5, R6]. This research, while still at an early stage,
has achieved significant practical impact through pre-publications and conference presentations to
academic and practitioner audiences. The practical impact, in turn, generated valuable feedback
shaping and enriching the research. The research has been presented at peer-reviewed academic
conferences and with the combined feedback is currently being prepared for submission to
academic journals, for example MIS Quarterly.
References to the research
[R1] Flyvbjerg, Bent, Garbuio, Massimo and Lovallo, Dan, 2009. Delusion and Deception in Large
Infrastructure Projects: Two Models for Explaining and Preventing Executive Disaster. California
Management Review, vol. 51, no. 2, pp. 170-193.
[R2] Flyvbjerg, Bent, 2009. Survival of the Unfittest: Why the Worst Infrastructure Gets Built—And
What We Can Do about It. Oxford Review of Economic Policy, vol. 25, no. 3, pp. 344-367.
[R3] Cantarelli, Chantal C., Flyvbjerg, Bent and Buhl, Søren L., 2012. Geographical Variation in
Project Cost Performance: The Netherlands Versus Worldwide, Journal of Transport
Geography, vol. 24, September, pp. 324-331.
[R4] Flyvbjerg, Bent, 2013. Quality control and due diligence in project management: Getting
decisions right by taking the outside view, International Journal of Project Management, vol. 31, no.
5, pp. 760-774.
[R6] Budzier, Alexander and Flyvbjerg, Bent, 2013. Making-Sense of the Impact and Importance of
Outliers in Project Management through the Use of Power Laws, 11th IRNOP Conference, Oslo,
June 16-18th, 2013 - the paper won the best presentation award at the IRNOP Conference.
British Telecom funded the research through the endowment of the chair of the BT Professor for
Major Programme Management and a very substantial 4 year research grant.
Details of the impact
The BTC has had an impact on a wide range of management and policy issues related to
megaprojects and major programmes in the UK and internationally. This case study highlights
three examples.
Improving Megaproject Decision Making in the UK Public Sector
The UK government concurrently manages circa 200 megaprojects, worth more than GBP 350
billion. BTC research has directly changed the way these investments are prioritized and assessed
through working in partnership with the UK's National Audit Office (NAO). Part of the NAO's remit
includes value-for-money studies, which look at how projects are implemented and how projects
can be improved. This joint interest between the NAO and the BTC led to an active collaboration.
In 2012, BTC and NAO held multiple full-day workshops in Oxford and London to share new
methods, research findings [e.g., R1, R2, R5], and collected data. In March-April 2012, the BTC
wrote a research report for the NAO to identify measures of project complexity with the aim of
identifying high-risk projects. The report was based on three years of research into project
complexity and early risk indicators [Section 5: C1]. 10 factors were identified, showing that risks
are mostly associated with the social and political environment of projects [C1]. In September
2012, the research was included in an internal report entitled `Designing successful projects and
programmes'. The report was combined with concurrent work by the Treasury's Infrastructure UK
group (IUK) to form the revised complexity assessment of government projects [C2, C3]. In
January 2013, the new complexity assessment was rolled out as part of IUK's route map toolkit
and applied to IUK's pipeline of 576 projects worth GBP 300 billion. The Director responsible for
this work at the NAO, said: "The global research [you] have been undertaking ... has proved an
invaluable source of evidence for the NAO ... Your analysis has made a substantial contribution to
the evidence base underpinning our research into the factors driving the success, or otherwise, of
major projects. An example of the impact which this work [has had is] our environmental
complexity analytic [which] forms the front end of the IUK Route map published earlier this year.
Your work — and importantly our discussions — was an important contributory evidence source."
[C4].
Achieving Impact through a Trusted Mediator
In 2009, the BTC was approached by McKinsey to begin a collaboration to widen the reach, and
transfer the research, in particular [e.g., R1, R2] into practice. From 2010-2012, BTC held multiple
full-day workshops with McKinsey in Oxford. The impact was two-fold. First, the research allowed
McKinsey to re-conceptualise their way of thinking about project management and subsequently
changed McKinsey's methodology in the light of the advocated reframing. In turn the impact
provided the data sources as well as relevant research questions that lead to [R5] and [R6]. The
McKinsey partners, who were involved, wrote that the "[McKinsey-Oxford] surveys of IT executives
indicate that the key to success lies in mastering four broad dimensions, which, combined, make
up [McKinsey's] methodology for large-scale IT projects that we call `value assurance'" [C5]. The
BTC research not only directly shaped the analytical tools of McKinsey's value assurance
framework but also identified and prioritized the dimensions for which practical solutions to project
problems are lacking. Subsequently, McKinsey has applied their new, BTC research-based, `value
assurance' methodology to advise more than 30 global clients between 2012 and 2013. The
cooperation with McKinsey allowed the BTC research to achieve a substantially more significant
impact with greater reach, by not only shaping a new consulting service, but also providing a
pathway for the BTC to achieve impact through other intermediaries, similar to McKinsey [C6].
A key Partner at McKinsey wrote: "Reflecting on the research project I see three areas of impact in
particular. First, the research created an empirical base to help us support the planning and
decision making of our clients. So far the data from your research was used at more than 20 of our
clients, who as a result have made a better informed decision. Secondly, your research has helped
us in developing an assessment framework which we use to analyse the complexities a project
faces and the organisational capabilities of our clients to deliver against that. Thirdly, your research
has helped us to dispel commonly held assumptions about the true risk drivers of projects, for
instance your insight that time is a much larger risk driver than project spend has led to an 11th
hour decision in one of our clients to not go forward with a 5-year, multimillion IT project" [C7].
De-Biasing the Largest Civil Project in the Developed World
The USD 51.8bn California High Speed Rail project is the US federal government's single largest
civil investment. Recent estimates total the cost of the two-phased development at approximately
USD 90bn. In 2012, after 5 years of planning, the US congress requested its auditor, the
Government Accountability Office (GAO), to review the final project plans. In autumn 2012,
drawing on the research [R1, R2] and Flyvbjerg et al. (2003) the GAO approached the BTC for
methodological advice on how to best establish an independent and unbiased view of the project.
Three high-ranking GAO officials interviewed the BTC Academic Director at length. In particular,
they were keen to learn more of the methodology developed by BTC for how to identify optimism
bias and strategic misrepresentation in project forecasts [R4]. The impact was two-fold. First, the
GAO adopted this methodology to define what it considers best practice. GAO's final report stated
"By not following all best practices, there is increased risk of such things as cost overruns, missed
deadlines, and unmet performance targets" [C8]. Out of five academic publications listed and used
by the GAO to identify global best practice, one article [R4] and two further publications (Flyvbjerg
et al. 2003, Flyvbjerg and COWI, 2004) were authored by BTC researchers [C8]. Secondly, the
BTC research changed how the GAO viewed the veracity of the plans, in particular the ridership
forecasts. GAO's Assistant Director, who led the project review, stated: "your work sensitized us to
issues of veracity. I think this was also true for California High Speed Rail Authority and Cambridge
Systematics. They seemed obliged to include low-ball ridership estimates, even though this took
some of the shine off their presentation.
"Your work was one of several factors we considered in reviewing the process used to prepare
ridership and revenue forecasts. It was not our intent to opine on the precise point estimates of the
forecasts but rather the process used to prepare the forecasts. If a sensitivity, and an extreme
downside, analysis had not been conducted we would have discussed this in the report and
suggested that it be addressed in future forecasts." [C9].
In sum, the research has impacted on the performance of a number of projects by changing the
way projects are planned, managed, and assured through multiple pathways of impact. The first
example achieved impact through changing the planning and decision making procedures of the
UK public sector through work with the National Audit Office (NAO). The second example achieved
impact to several large-scale projects in the private sector through collaborating with McKinsey &
Company, as a trusted mediator. The third example showed the impact on a specific project,
California High Speed Rail, which made the project team consider more realistic and de-biased
cost and revenue forecasts.
Sources to corroborate the impact
[C1] National Audit Office, 2012. Designing successful projects and programmes, London — unpublished report.
[C2] Infrastructure UK (IUK), 2013. Infrastructure Procurement Routemap: a Guide to Improving
Delivery Capability, London: HM Treasury.
[C3] Audit Manager, UK National Audit Office — will confirm the impact on the NAO's internal
thinking on how to design and execute successful projects
[C4] Director, UK National Audit Office — Held on File — confirms the impact on IUK route map
[C5] Bloch, Michael, Blumberg, Sven, and Laartz, Jürgen, 2013. Delivering large-scale IT projects
on time, on budget, and on value. McKinsey on Business Technology, 6 pp.
[C6] Director, McKinsey & Company, Inc. — will confirm the impact on McKinsey's Value Assurance
service line and the impact of the collaboration
[C7] Expert Principal, McKinsey & Company, Inc. — Held on File — confirms the impact on
McKinsey's thinking and their clients
[C8] United States Government Accountability Office, March 2013. CALIFORNIA HIGH-SPEED
PASSENGER RAIL Project Estimates Could Be Improved to Better Inform Future Decisions, GAO-13-304,
Washington, D.C., 90 pp.
[C9] Assistant Director, US Government Accountability Office — Held on File — confirms the impact
on California High Speed Rail